State of the Art Nitrogen Upgrade Program (SANUP)
Package A - Supplemental Carbon Improvements

21 April 2010: Pre-Bid Meeting
10 May 2010: Addendum 1 (open/download pdf):
WMBE and Wage Rates released
 

     
   
 

Bid Date
2:00 pm, 12 May 2010

Project Location
1500 Eisenhower Ave, Alexandria VA 22314

Owner
Alexandria Sanitation Authority

Estimated Value
$1,000,000

 




Submit Proposals to

American Contracting and Environmental Services, Inc.
1002 West Street, Laurel, MD 20707
Phone (301) 490-9100
Fax (301) 490-9101

   
 
Project Description:
 
Alexandria Sanitation Authority is planning upgrades that will reduce the amount of nutrients discharged in wastewater effluent to meet environmental regulations. The SANUP project is estimated to cost $82 million dollars and complete in 2014. The first contract for this project is Package A--Supplemental Carbon Improvements. This work includes:
  • Replacing the existing two methanol storage tanks and six feed pumps.
  • Repurposing two of the four FeCl3 storage tanks in Building L for storage and feed of supplemental carbon.
  • Repurposing the two NaOH storage tanks in Building L for storage and feed of supplemental carbon.
  • Installing additional piping from Buildings L and M  to the Biological Reactor Basins (BRBs) and to the Centrate Pretreatment Facility (CPT).
  • Providing other miscellaneous improvements.
 

webassets/ASAplant.jpg